Misr Beni Suef Cement Company produces cement products through two production lines:
First Production Line
The company has contracted on the supply and installation of the necessary equipment and machinery to operate the first
first production line (in 1998 and the start of actual production at the beginning of 2003) with a production capacity of one and a half million tons per year.
Second Production Line
The company has contracted on the supply and installation of the necessary equipment and machinery to operate the first
The company has contracted on the supply and installation of the necessary equipment and machinery to operate the second production line (in 2006 and the start of actual production at the beginning of 2010) with a production capacity of one and a half million tons per year, and the aim of operating a new production line was to obtain a larger production capacity to cover the needs of the local market.